2023 £ per tonne (costs) | January | February | March | April | May | June | July | August | September | October | November | December |
---|---|---|---|---|---|---|---|---|---|---|---|---|
EfW* | 88 - 112 | 88 - 112 | 88 - 112 | 90 - 114 | 93 - 119 | 93 - 119 | 93 - 119 | 93 - 119 | 93 - 119 | 95 - 118 | 95 - 118 | 90 - 116 |
Landfill | 19 - 30 | 19 - 30 | 19 - 30 | 20 - 30 | 20 - 30 | 20 - 30 | 20 - 30 | 20 - 30 | 20 - 30 | 20 - 30 | 20 - 30 | 20 - 30 |
Landfill + tax | 117.60 - 128.60 | 117.60 - 128.60 | 117.60 - 128.60 | 122.10 - 132.10 | 122.10 - 132.10 | 122.10 - 132.10 | 122.10 - 132.10 | 122.10 - 132.10 | 122.10 - 132.10 | 122.10 - 132.10 | 122.10 - 132.10 | 122.10 - 132.10 |
RDF export** | 90 - 101 | 90 - 101 | 90 - 100 | 88 - 102 | 88 - 102 | 88 - 102 | 88 - 100 | 88 - 100 | 88 - 100 | 86 - 98 | 86 - 98 | 89 - 100 |
* gate fee to UK plant
** includes transport from RDF producer site; producer also has to meet baling/wrapping costs of c£15+